This project entailed 4-hour fire rated bulk diesel tanks as a secondary fuel supply for the main steam and hot water boiler systems.
The systems were installed after the plant rooms had been constructed and fitted out, installation of the equipment had to be installed using specialised rigging equipment due to spatial constraints.
- 4-hour fire rated bulk tanks
- Tank stands
- Fuel transfer pipe work
- Automatic control systems
- Interface to the sites existing diesel fuel system
- Transport to site for all equipment
- On-site installation
- Site commissioning
- Electrical design
- Mechanical Design
- Project management